Sweetwater, Oregon

Digital Mapping & Hydrology

SOA mobilized to deliver a comprehensive survey of this 850 acre area, determining its suitability for a ground-mount solar installation.

Turnaround time was extremely limited by the client’s time frame for acquisition and permitting process. Notice to proceed was granted six days before reporting was due. SOA field teams mobilized quickly to acquire necessary data sets, operating through a snow and wind storm to survey total site area in 72 hours. The base map was then used for hydrologic analysis of the site.

Total package was delivered within six days of NTP.